Project Description
Department of Immigration & Border Protection
Client: Metrowest Constructions
Consultant: PGD Consulting Services
Architect: N/A
Value: $200 K
The DIBP Offices are located at Perth International Airport, Terminal 1 Departures. The scope of work involved the expansion of an existing CCTV server room.
MPS were engaged to supply and install a new APC CRAC system which consisted of hot and cold row in-row coolers, roof mounted condensers, liquid line receivers and interconnecting pipework. Additional to these works existing ductwork is to be modified by installing security mesh to ensure the required security level in server room is achieved.
MPS carried out the works in a fully occupied secure office environment within a fully operational departure terminal. The works have required careful planning with preparation of fully documented methodologies being issued for the approval of the airport authority, prior to commencement of works.
This project was completed in March 2017.